Jonathan Ochshorn Room 121-B, Rand Hall Department of Architecture Cornell University |
contact: questions and comments back to homepage | ||||
| ARCH 262: Building Technology, Materials & Methods Course Outline, Fall 1999 | |||||
| week | date | topic | reading | assignments | |
| Introduction | 1 | Aug. 30 | Course overview/building systems | ch. 1 | |
| Sept. 1 | Wood: properties and details | ch. 3 | |||
| 2 | Sept. 6 | Wood frame construction | ch. 5-7 | assign#1 issued (wood frame) | |
| Sept. 8 | Roofing: steep-slope | ch. 16 (592-606) | |||
| 3 | Sept. 13 | Gypsum board | ch. 23 | ||
| Sept. 15 | Foundations | ch. 2 | assign#1 due | ||
|
Construction of structural systems | 4 | Sept. 20 | Bearing wall systems | ch. 10 | assign#2 issued (bearing wall) |
| Sept. 22 | Masonry: material properties; construction details | ch. 8,9 | |||
| 5 | Sept. 27 | Concrete: material properties; construction details | ch.13 | ||
| Sept. 29 | Structural frame systems | ch.11 (344-383) | assign#2 due | ||
| 6 | Oct. 4 | Steel: properties and details | ch.11 (384-414) ch.12 | ||
| Oct. 6 | Concrete frame; heavy timber | ch. 4,14 | final project issued | ||
|
Enclosure systems | 7 | Oct. 11 | FALL BREAK/NO CLASS | ||
| Oct. 13 | Water, air infiltration, insulation, condensation, ventilation | ch.16 (572-576) | |||
| 8 | Oct. 18 | Movement, joints, sealant joint calculations | ch.19 (684-688) | assign#3 issued (sealant joint) | |
| Oct. 20 | Barrier, cavity, rain-screen walls | ch.19 (674-683) | |||
| 9 | Oct. 25 | Brick, stone veneer | ch.20 (692-703) optional | assign#3 due | |
| Oct. 27 | Precast concrete, metal panels | ch.15 ch.20 (704-710) | assign#4 issued (cavity wall) | ||
| 10 | Nov. 1 | Alum-glass curtain walls; glazing | ch. 17,18,21 | ||
| Nov. 3 | EIFS | ch.20 (710-714) | |||
| 11 | Nov. 8 | Roofing: low-slope (video) | ch.16 (566-571; 576-591) | assign#4 due | |
|
Interior systems | Nov. 10 | Ceiling, wall, floor systems | ch.22,24 | assign#5 issued (curtain wall) | |
|
Fire protection | 12 | Nov. 15 | Overview of fire safety issues | see ref. #17 | |
| Nov. 17 | Occupancy, construction types; case study |
see ref. #7 (ch. 2) | assign#5 due | ||
| 13 | Nov. 22 | Fire-rated assemblies | see ref. #19 | assign#6 issued (code issues) | |
| Nov. 24 | Egress systems |
see ref.#5 see ref.#7 (ch.9) | |||
| Accessibility | 14 | Nov. 29 | Ramps, doors, bathrooms | see ref.#13 | assign#6 due |
| Dec. 1 | NO CLASS | ||||
| Dec. 14 | Final exam, 12:00 noon Goldwin Smith D | final project due* | |||
*bring final projects to RAND 121, or hallway in front of RAND 121, before final exam. | |||||
| last updated: 2 November 1999 Copyright 1999 J. Ochshorn. All rights reserved. Republishing material on this web site, whether in print or on another web site, in whole or in part, is not permitted without advance permission of the author. |
|||||