week date topic reading assignments

Introduction 1 Sept. 2 Course overview/building systems ch. 1

Construction
of structural
systems
Sept. 4 Concrete: properties, reinforcement ch. 13

2 Sept. 9 Foundations ch. 2
Sept. 11 Wood: properties ch. 3

3 Sept. 16 Wood frame construction ch. 5-7 assign#1 issued
(wood frame)
Sept. 18 Roofing: steep-slope ch. 16 (592-606)

4 Sept. 23 Masonry: properties (stone, brick, block) ch. 8,9
optional stone essay
Sept. 25 Bearing wall systems (incl. heavy timber) ch.4,10

5 Sept. 30 Steel: properties ch.11 (384-414)
ch.12
optional steel essay
assign#1 due
Oct. 2 Structural frame systems ch.11 (344-383)
ch.14

Enclosure
systems
6 Oct. 7 Water, air infiltration,
insulation, condensation,
ventilation
ch.16 (572-576)
Oct. 9 (previous topic continued) final project
issued

7 Oct. 14 [fall break/ no class]
Oct. 16 Movement, joints, sealant joint
calculations
ch.19 (684-688) assign#2 issued
(sealant joint)

8 Oct. 21 Barrier, cavity, rain-screen walls ch.19 (674-683) assign#2 due
Oct. 23 Brick, stone veneer ch.20 (692-703)
optional brick essay
assign#3 issued
(cavity wall)

9 Oct. 28 Precast concrete, metal panelsch.15
ch.20 (704-710)
Oct. 30 Alum-glass curtain walls; glazing ch. 17,18,21
optional curtain wall essay

10 Nov. 4 EIFS ch.20 (710-714) assign#3 due
Nov. 6 Roofing: low-slope (video) ch.16 (566-571;
576-591)

Interior
systems
11 Nov. 11 Gypsum board ch.23
Nov. 13 Ceiling, wall,
floor systems
ch.22,24

Fire
protection
12 Nov. 18 Overview of fire
safety issues
see ref. #17
Nov. 20 Occupancy, construction types;
case study; handout
see ref. #7
(ch. 2)

13 Nov. 25 Fire-rated assemblies see ref. #19 assign#4 issued
(code issues)
Nov. 27 Egress systems see ref.#5
see ref.#7 (ch.9)

Accessibility 14 Dec. 2 Ramps, doors, bathrooms see ref.#13 assign#4 due
Dec. 4 NO CLASS

Dec. 12 Alternate Final exam, 3:00-5:30 pm
Room 101 WS

Dec. 18 Final exam, 3:00-5:30 pm
Room 157 ES
final project due*

*bring final projects to RAND 121, or hallway in front of RAND 121, before final exam.
last updated: 10 December 2002

Copyright 2002 J. Ochshorn. All rights reserved. Republishing material on this web site, whether in print or on another web site, in whole or in part, is not permitted without advance permission of the author.